Under the directives of His Highness Sheikh Mohammed bin Rashid Al Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, may God protect him, His Highness Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, Deputy Prime Minister, Minister of Defense, and Chairman of The Executive Council of Dubai, announced the award of new contracts worth approximately AED 56.5 billion as part of the development of Al Maktoum International Airport.
The latest awards bring the total value of contracts awarded under the project to approximately AED 80 billion.
The project is now entering a major construction phase covering passenger terminals, aircraft concourses, transportation and energy facilities, infrastructure, and essential airport services. This phase supports Dubai’s efforts to maintain its position among the world’s leading aviation hubs while meeting the industry’s future growth requirements.
Mohammed bin Rashid’s Vision Strengthens Dubai’s Global Aviation Leadership for Decades to Come
His Highness Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum said, “The vision of His Highness Sheikh Mohammed bin Rashid Al Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, may God protect him, has established Dubai’s position at the forefront of global aviation hubs. Under His Highness’s directives, we announce today the award of new contracts worth approximately AED 56.5 billion as part of the Al Maktoum International Airport project, as we move forward with the completion of Dubai’s new global airport and consolidate the emirate’s leadership in the aviation sector for decades to come.”
His Highness added, “Al Maktoum International Airport is a project for generations and a strategic investment in Dubai’s future, economy, and global standing. What is being achieved on the project site embodies Dubai’s approach to turning ambitious visions into achievements, enhances its ability to accommodate the expected growth in passenger and cargo traffic, and supports the objectives of the Dubai Economic Agenda D33 to double the size of the emirate’s economy and expand its connectivity with global markets.”
A New Phase of Development for the World’s Largest and Best Airport
In a post on the social media platform X, His Highness Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum highlighted the scale of the project and its future capacity.
His Highness said, “Under the directives of His Highness Sheikh Mohammed bin Rashid Al Maktoum, we announce today the award of new contracts worth AED 56.5 billion as part of the Al Maktoum International Airport development project, bringing the total value of contracts awarded under this strategic project to more than AED 80 billion. With the award of these contracts, we embark on a new phase in the development of the world’s largest and best airport, which is being delivered by a team of 14,000 people. Upon completion of all its phases, Al Maktoum International Airport’s annual passenger capacity will exceed 260 million, ensuring that Dubai remains the world’s airport and destination.”
Unprecedented Infrastructure Investments to Serve Future Generations
His Highness Sheikh Ahmed bin Saeed Al Maktoum, Chairman of Dubai Aviation City Corporation and Chairman of Dubai Aviation Engineering Projects, confirmed that the development of Al Maktoum International Airport has entered a phase of large-scale construction.
He noted that the value of the newly awarded contracts represents an unprecedented milestone in the development of infrastructure projects in Dubai and the UAE, reflecting both the exceptional scale of the airport project and the accelerating pace of construction.
His Highness said, “These contract awards represent a historic milestone in the implementation of the project. This unprecedented volume of contracts reflects the scale of the project and the investment Dubai is making today to build infrastructure that will serve future generations and support the growth of the aviation sector and the economy for decades to come.”
His Highness added, “We are moving forward with the completion of the first phase in accordance with the approved program. Contracts and implementation phases have been arranged to ensure that work continues in parallel across multiple sites while maintaining the highest standards of quality and safety. Once operational, the airport will provide Dubai with the capacity it needs to keep pace with the growth of national carriers and the expected increase in passenger and cargo traffic over the coming decades.”
Construction Progress Across Passenger Terminals and Essential Airport Facilities
During the previous phase, Dubai Aviation Engineering Projects awarded contracts and work packages worth approximately AED 23.815 billion. These covered enabling works and substructure construction across several project sites, along with contracts for the automated passenger transportation system and baggage handling system.
With the latest contracts awarded, construction activity continues to expand across passenger terminal areas, aircraft concourses, tunnels, transportation facilities, and airport services.
Enabling works in the areas of Concourses 2 and 3 and the central section of the airport site are nearing completion. Work is also progressing across the central passenger terminal area, the ground transportation center, and Concourse 4.
Excavation work completed across the project has exceeded 24.23 million cubic meters, while backfilling has surpassed five million cubic meters. A total of 7,635 foundation piles have also been installed.
14,000 Workers and More Than 21 Million Work Hours Advance Airport Construction
Construction teams continue to make progress across the airport development site, with more than 875,603 cubic meters of concrete poured as part of the substructure work packages covering Concourses 2 and 3, baggage handling system tunnels, and ground service equipment routes.
More than 226,000 metric tons of reinforcing steel have also been installed in preparation for the construction of above-ground structures.
Approximately 14,000 people are working across these construction packages, with more than 21 million work hours completed to date.